Tuesday, Wednesday & Thursday
Oct. 28th, 29th & 30th
 

The west wall is adjusted and anchored to the deadmen posts with cables.

Tubing/drain tile is attached along the walls before they are backfilled with dirt.

Mike removes the pump used to keep the harbor dry and the water is pumped back in so the dirt at the entrance doesn't wash back into the harbor.

 
 
Mike works behind the crew to add extra cable ties, preventing any slipping of the cables in the future.
 
Extra support rods are added to the angle walls on the entrance to tie the poles to their current position and for added strength.
The new entrance angle wall is built behind the old wall.  The entrance posts are positioned and the last wall section is brought in after the water is pumped back in.
  
More Harbor
Renovation Photos
(Click on a day to view photos)

Friday & Saturday, Oct. 17 & 18

Wednesday-Friday, Oct. 22-24

Saturday-Monday, Oct. 25-27

Friday & Saturday, Oct. 31-Nov. 1

Tuesday, Jan. 20

 
 
 

Copyright © 2006-2008 Woodland Resort